• Grey Twitter Icon
  • Grey LinkedIn Icon
  • Grey Facebook Icon
Screenshot 2019-03-29 at 08.06.47.png

Waitings Ltd, Moss Road, Cliburn, Penrith, Cumbria, CA10 3AL 

Ipswich Tidal Barrier
Dredging of river bed silts and installation of rock armour
Great Ayton WwTW
Construction of RC Humus Tank & associated inter connecting pipework
Dragley Beck Pumping Station
Installation of cofferdams and RC structures and the associated interconnecting pipework
Raby Cote TES
installation of a new gravity fed 400/450mm ductile Iron main with Pre-fabricated inspection chambers
Horncastle FAS
Specialist plant hire for the construction of new flood defences.
Wreay Solar Farm
Installation of approximately 24km of ducting and cabling from the wind farm to a grid connection point. This involved burying over 150,000 meters of ducting and winching in the 33kV cable.
Greenport Hull
Longreach hire for dredging works and assistance with the tie rod installation
London City Airport
Specialist GPS controlled longreach equipment and attachments for UXO clearance in advance of the main airport extension works.
Glasson Dock
Relining of existing tidal outfall and installation of new flap valves.
Amble Dredging
Assisting with the assembly and movement of the floating lines.
Ray Windfarm
Waitings were contracted to install approximately 24km of ducting and cabling from a wind farm 20 miles north of Hexham, to a grid connection point at a local distribution network operators substation.
Pontoon Dredging
Maintenance dredging to ferry pontoon using a variety of different methods and assisted by a large cutter suction dredger.
Carlisle Cycle Track
Construction of a new cycle track and all associated landscaping works.
Carlisle Airport
Cut and fill exercise on the runway and installation of service ducting
Blackpool Sewer Installation
Installation of large diameter pipelines
Installation of 300m sheet piles
Construction of large attenuation basin
Burnfoot Wind Farm
Burnfoot Wind Farm was a project that Waitings initially worked on over five years ago, installing the ducting and cables for the exporting of electricity to a substation at Alva in Sterling, Scotland.
Start up to Waste
Framework agreement for the completion of various works to ensure consent dates were met.
Cockermouth WwtW
Multi site contract to include the construction of new concrete structures and installation of associated pipework and ducting and 8m deep wetwells.
Wetheral WwTW
Installation and excavation of 2 no. cofferdams. Installation of associated ducts and pipework.
Timber Groyne Repairs
Repairs to timber groynes to include new timber piles and timber works
Egremont Pipeline
Waitings were honoured to work on an 11 km section of the south Egremont pipeline. The project was part of a large scheme to replenish water to Ennerdale Lake
Safety Boat Cover
Providing one of our 5m ribs for safety boat cover on marine cofferdam.
Bridge Investigation Works
Hire of modular pontoons from our sister company PSUK. www.pontoonsolutionsuk.com
Berthing Pontoons
Installation of the dockside berthing pontoon at Victoria Quays.
Tidal River Dredging
Dredging of approximately 3km of tidal river. The works included working from pontoons in open water and additional activities under Network Rail bridge assets on the West Coast Mainline.
Kirkby Stephen Gauging Station
Maintenance dredging to ensure the continued use of the station.
Williamsgate Land Drainage
Design and installation of large land drainage scheme
River Lowther Fish Pass
Removal of existing weir to include installation of scour protection and underpinning works to existing bridge piers.
Cleethorpes Terminal Groyne
Unloading and transportation of 13500te of Norwegian rock armour.
Tyrer Bridge
Removal of flood debris and re-profiling existing batter to include scour protection to toe and installation of erosion matting.
Show More