Dragley Beck Pumping Station

​

Duration: 4 months

​

Installation of cofferdams and RC structures and the associated interconnecting pipework

6 no. cofferdams were installed using our in house piling equipment and sheet piles from our existing pile stock. The RC structures were constructed within the cofferdams and the 1200mm dia. interconnecting pipe installed between the chambers